#initializeObject



3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
# File 'lib/asposetasksjava/Tasks/changeprogressoftask.rb', line 3

def initialize()
    data_dir = File.dirname(File.dirname(File.dirname(File.dirname(__FILE__)))) + '/data/'
            
    # Instantiate project object
    project = Rjb::import('com.aspose.tasks.Project').new

    puts project.getCalculationMode()

    task = project.getRootTask().getChildren().add("Task")

    tsk = Rjb::import('com.aspose.tasks.Tsk')

    task.set(tsk.DURATION, project.getDuration(2))

    task.set(tsk.PERCENT_COMPLETE, 50)

    puts "Changed progress of task."
end